New sewer line project progresses on schedule despite May weather setbacks
A dramatic rise in the water table after May’s flooding weather event has made life tricky for contractors working on a new sewer line near the Ashburton River, but the project is still on track and making good progress.
Council contractors Seipp are laying just over 2km of pipe from the river’s edge at Milton Road South to Wakanui Road, where it will link with a 3km section of pipe being laid by Ashburton Contracting Ltd (ACL).
The $10 million project, known as the Ashburton Relief Sewer, will provide new sewer lines to the town’s treatment facility to cope with the expected growth in the decades to come.
Funds for the project include $8 million from Government as part of a Covid stimulus package. Government project engineers were in town last week to check on the progress of the project, to ensure deadlines were being met and that funds were being well spent.
At Milton Road South they saw where the pipe is being buried at least 6 metres deep. Contractors said the water table in the area had risen by 1.5 metres after heavy rain caused flooding in the Ashburton River on 31 May. They are sheet piling the deep channel being dug for the pipe so water can be pumped out of the workspace.
At the river, the pipe links to the Ashburton River Crossing and Pump Station, completed last December.
ACL has been working along Wakanui Road and has now moved onto Albert Street, where the pipe will run for several hundred metres before turning towards Mill Creek. The final leg will run alongside the creek to Bridge Street.
Infrastructure Services Group Manager Neil McCann said the work was a sizable upgrade.
"The roads that have been temporarily closed are being re-opened to the public as soon as possible.
"Wakanui Road re-opened on Friday and its berms will be reinstated in warmer weather," he said.
ACL expects to be working on Albert Street for 10 weeks and the street will be closed to all non-resident road users. Albert Street residents, Ashburton Christian School staff, students and parents will still have access to the school and their homes.
The project is expected to be completed by March 2022.
To stay informed of updates by visiting the ARS Project page.
Share this article
Latest News
Rangitata SH1 bridge pile repair underway
'There be dragons' at the Ashburton Library these school holidays
93% of Glow waste diverted from landfill
Cr Phill Hooper: Steering against the negative drift
Water meter data will help prioritise pipe renewal
Road Closures
LAURISTON BARRHILL ROAD
from 24 Jun 7:00 to 12 Jul 17:00
STANLEY ROAD - TAVERNERS ROAD - DROME STATION ROAD INTERSECTION
from 16 Jun 7:00 to 17 Jun 17:00
WINDERMERE ROAD
from 26 Jun 7:00 to 3 Jul 18:00
GRACE IRELAND DRIVE METHVEN
from 20 May 7:00 to 31 Aug 17:00
BARKERS ROAD
from 12 Jul 13:00 to 14 Jul 18:00
View all Road Closures | Live map