banner image

Stockwater Exit Transition Plan

Transition Plan Adopted (December 2024)

On 18 December 2024, Councillors adopted the Stockwater Exit Transition Plan that will usher Council out of the business of delivering stockwater by 2027.

The plan clearly sets out the process Council will take in exiting the service, the intakes and various water sources that feed the stockwater network.

Included in the plan is a programme setting an approximate order of work which will be undertaken on an intake by intake basis. If you want to find which intake your stockwater comes from, refer to the intake maps in the plan.

Below is a summary of the intended programme – the full programme can be viewed in the plan.

Task:

Duration

Start

Finish

Stockwater Exit Transition Plan Programme

675 days

27/09/24

30/06/27

Pudding Hill Intake (early work has been completed)

286 days

27/09/24

26/11/25

Methven Auxiliary Intake

363 days

13/01/25

01/07/26

Bushside Intake

178 days

13/03/25

26/11/25

Stoney Creek Intake

180 days

24/04/25

16/01/26

Limestone Creek Intake

163 days

05/06/25

02/02/26

Alford Forest Intake

40 days

16/07/25

09/09/25

Brothers Intake

303 days

23/06/25

09/09/26

Langdons North & South Intakes

187 days

13/08/25

19/05/26

Clearwell Springs Intake

168 days

22/09/25

02/06/26

Cracroft Intake

284 days

23/10/25

17/12/26

Klondyke Intake

215 days

12/12/25

28/10/26

Shepherds Brook Intake

178 days

05/02/26

20/10/26

Remmington Creek Intake

178 days

18/03/26

01/12/26

Lagmhor Creek Intake

196 days

30/04/26

12/02/27

Winchmore Intake

215 days

16/06/26

29/04/27

Rokeby Intake

137 days

29/07/26

17/02/26

Acton Intake

200 days?

07/09/26

30/06/27

Stockwater Transition Working Group (September 2024)

The Stockwater Transition Working Group (STWG) was established as a result of Council’s Long Term Plan decision to exit the provision of stockwater across the district.

The STWG membership includes:

  • Cr Richard Wilson (Chair)
  • Cr Carolyn Cameron
  • 1 x Federated Farmer representative
  • 1 x Environment Canterbury representative
  • 1 x Te Rūnaka o Arowhenua representative
  • 1 x Consultant Resource (Melius Ltd - John Wright)

The first deliverable for the working group was the development of the Stockwater Exit Transition Plan (SETP) by December 2024. The plan was developed internally by staff with the assistance of Aoraki Environmental Consultancy Limited (AECL) and the project consultant.

Background (June 2024)

On 26 June 2024, Council adopted its 2024-2034 Long Term Plan (LTP) which included the decision to divest itself from the delivery of the stockwater services by 30 June 2027.

Funding has been included in the LTP for a managed and inclusive exit of the Council delivering stockwater, with a stockwater working group being established to monitor progress.  It is anticipated that most properties will be able to be supplied with stockwater from an alternative supply such as an irrigation company or the like.

The key reasons for Council ceasing to deliver stockwater by 30 June 2027 are:

  • The stockwater network is an ageing and inefficient method of delivering water for livestock to farms.
  • Maintaining the system is getting costlier because the infrastructure is ageing and needs replacement. Many components, related to the channels (eg race gates, junctions, flumes) will need replacing over the next few decades.
  • The service relies on having sufficient water in the system to keep the water flowing. During summer, water sources often dry up, meaning we can’t always guarantee the service.
  • There are other, more modern ways for properties to get stockwater. A lot of people who pay for this service don't use it because they've found more efficient ways to get stockwater such as through irrigation schemes.
  • Meeting new environmental requirements will add extra cost to ensure the system is viable in the future. For example, this includes the installation of fish screens on some intakes to meet these new standards.

All properties that have stockwater races running through them will be consulted with during the divestment process.  Some races may not be closed due to ecological values or for other reasons and this will be considered and worked through as part of the process.

Sign up for information and regular updates


Project News

Progress made on plan to exit stockwater delivery

Council is progressing work on a transition plan to exit its stockwater delivery service.

Stockwater update: 14 June 2024

Council is reminding farmers new to the Ashburton District that animals drinking from stockwater races need to be at a properly formed drinking bay.

LTP: Stockwater service in the spotlight

Council’s stockwater system was once a crucial open race network delivering water to farms around the district, but by today’s standards it is an inefficient and expensive way to deliver water to livestock.

Stockwater flows under pressure

Reduced river flows and hot weather are putting pressure on Council’s stockwater network, with subsequent declining flows in the race network.